The application is the middle of the process, not the start of it. In Indiana the soil work comes first, the design follows the soil, the county reviews the two together, and the permit is signed by the health officer before any digging happens. Getting the order right is most of what separates a permit that moves from one that sits.

What is the order?

  1. An on-site soil evaluation, with the profile described by a soil scientist.
  2. A system design that suits what the soil evaluation found.
  3. The county application, with the property information, the soil evaluation and the design.
  4. The county's written decision, issued or denied by the health officer.
  5. Construction by the installer your county allows to do the work.
  6. The county's inspection before the system is covered.

Source: 410 IAC 6-8.3-56(a) to (c), read 2026-08-20.

Whose name goes on the permit?

The rule puts the duty on the owner or the owner's agent to obtain the permit. In practice a contractor often applies as your agent, which is fine and normal, but the obligation is still attached to the property owner. Ask who is applying before the paperwork goes in.

Source: 410 IAC 6-8.3-53(a), Indiana Administrative Code, read 2026-08-20.

What do I need to have ready?

  • The property information the county asks for on its own form, including the parcel.
  • The soil evaluation report.
  • The system design, often as a scale drawing.
  • The number of bedrooms, which sizes the system.
  • The county's fee, which every county sets for itself.

Your county health department's own page is the authority on the form and the fee. This page describes the shape of the process, not one county's paperwork.

How long does it take?

That depends on the county, the season and how busy the soil scientists are. What we will not print is a statewide number of days, because the counties do not share one. Ask your county when you file, and plan the build around the answer rather than around a number from the internet.

What if the county denies it?

A denial is written, and the rule provides for appeals, including an option for the parties to use the state's Administrative Orders and Procedures Act procedures. Most denials in practice are a design the soil will not support, which sends you back to the design rather than to a lawyer.

Get help with the county application

Tell us the county and the job. No email needed.

A marketing service, not a licensed contractor. Septic work is performed by independent local contractors.

By submitting this form, I agree that Compass Camper LLC and a septic contractor may contact me at the phone number I provided, including by automated phone calls and prerecorded messages, regarding septic services. Consent is not a condition of any purchase. Message and data rates may apply. I may opt out at any time by asking to be removed during any call. See our Privacy Policy.

Your request goes to an independent local septic contractor serving your Indiana county, not a national lead list.

Prefer to talk? Call (317) 978-3952.

Need the job done, not just the rule explained

Your request goes to an independent local septic contractor serving your Indiana county, not a national lead list.

Tell us the county and the job

Last reviewed 2026-08-20.

(317) 978-3952